Tuesday
- attach side wall
- cut out and arrange planks for bay window
- texture planks for bay window
- glue together ground floor room
- plank the deck
- work out multiple options for wood finish
- use the maple strips to plank a wall area
- fix the problems with the split level floor
- increase height of split level by cutting front wall
- attach walls on remaining side
Wednesday
- dremel another railing from dowel (in box ready to be moulded)
- cut out roof for front and bay window
- reference shingles and design rear roof
- whatever I didn't get done from Tuesday
Over Easter
- draw out plan for upper roof deck
- draw out plans for stairs (x2)
- figure out how the hell to plank the raft!
- plank the raft
- roofing. lots of it.
- make doors
- perspex or acetate in windows
- foamex window frames
- make shutters (with itty bitty hinges)
- draw out plan for boat balcony (foamex?)
- figure out how i'm doing the dome
- paint all the inside? what colour? photos?
- have stuff ready to go for workshop after holidays
After Easter
- make silicone mould of railing #1
- make silicone mould of railing #2
- cast loads of railings in resin
- make boat balcony
- CNC wheel and front shack
- ***motor for wheel ***
- cut out tower roof
- double vac-form dome for roof
- do out the dodecahedrons or whatever the hell they are on the dome
- flooring for the observation deck
But Wait, There's More!
- make barrels
- make chimneys
- bend and attach LOTS of pipes (make corner joins)
- gutters
- make balconies
- birdcages
- butterfly nets
- car tyres
- weather instruments
- find, buy or make lights (dolls hospital)
- finishing details: dirt, moss, rust etc.
- all the editing and schizz for john buckley
- You are so screwed